CN
CN
Hai'an 3.1MW Rooftop Solar Panels
2024-05-09

On 30th June 2022, a 3.1MW rooftop PV array installed at CNTY's Headquarters was successfully connected to the grid. Utilizing about 26,000m2 of our workshop rooftops, the 550Wp monocrystalline PV panels have a capacity to generate 3,259,500 kWh of electricity annually, saving about 1,271 tons of coal equivalent and reducing CO2 emissions by 3,249 tons. The power generated is used for factory production within the HQ, reducing the cost of utility while building a green and low-carbon industrial park.